Remodel order of work: what has to come first, and what varies

A permit, safety checks and rough-in inspections have a fixed place in the job. Paint, floors and cabinets do not.

By RenovaOak Editorial Team Updated 7 min read

What it covers
Permit to punch list
Fixed points
Permit, rough-in, final
Varies by job
Paint, floors and cabinets
Ask for
A written schedule
Illustration: a wall in cross section at four stages, framing, pipes and wires inside the studs, drywall, then paint and trim
Each stage covers the one before it, which is why the inspections come in between.

In short

The order below is a trade convention, not a rule. Crews change it to fit the house, the trades and the materials. A few points are not up to the crew: the model building code says a permit comes before the work, plumbing, electrical, gas and mechanical rough-in is inspected before it is covered, and a final inspection comes after the permitted work is done. In an older house, lead and asbestos questions come before demolition. Everything in between, especially paint, floors and cabinets, is sequenced differently by different crews, so ask for the schedule in writing.

A convention, with a few fixed points

Nobody publishes one official order of work for an interior remodel. What you will hear from contractors is a convention: demolish, build the structure, install the hidden systems, close the walls, finish the surfaces, then connect and trim. It exists because each stage covers the one before it, so mistakes found late cost the most to fix. A kitchen with a new layout and a basement with new framing do not run in the same sequence.

Some points in the sequence do come from rules rather than habit. This page marks which is which. The code points below come from the International Residential Code (IRC), a model code. Your state or city adopts a particular edition, often with changes, and your building department decides what applies to you.

The usual order, step by step

This is the typical sequence for a job that opens walls. A cosmetic refresh skips most of it. Use it to check your contractor's schedule, not as the schedule.

  1. Permit. The model code says an owner or agent who intends to alter a building, or to install or replace a regulated electrical, gas, mechanical or plumbing system, applies to the building official first and gets the permit (IRC R105.1). See permits for interior remodels for what usually needs one.
  2. Lead and asbestos checks, in an older house. These come before demolition, because the answer can change who may do the work and how the dust is controlled. Lead paint and asbestos in older homes goes through it.
  3. Protect the house and demolish. Floors, openings and air paths are covered, then the surfaces that are coming out are removed.
  4. Structure. Framing changes, such as a removed or moved wall, come before new pipes and wires are run through them. See open floor plans and moving walls.
  5. Rough plumbing, electrical and mechanical. Pipes, wires, gas lines and ducts go in while the framing is still open. This is the work that follows the layout, so the layout has to be settled by now.
  6. Rough-in inspection. Inspected before anything covers it (IRC R109.1.2).
  7. Insulation and drywall. The walls close. Drywall repair and texture covers taping, finishing and texture.
  8. Paint, floors and cabinets. The order here is the one that varies most; the next section explains why.
  9. Finish plumbing and electrical. Fixtures, faucets, outlets, switches and lights are set once the surfaces around them are done.
  10. Trim and doors. See trim, doors and wall finishes.
  11. Final inspection and punch list. The final inspection is made after the permitted work is complete (IRC R109.1.6). The punch list is your walk-through list of small fixes, and the last payment should wait until it is done.

Room pages show how the sequence plays out in one space: kitchen remodel, bathroom remodel, lighting and electrical updates and basement finishing.

What the code and EPA pin down

Four points in the sequence are anchored by sources, not by custom.

  • Permit before work. Under the model code, the permit comes first. Some finish work is exempt from a building permit in the model code, including painting, papering, tiling, carpeting, cabinets and counter tops, but the exemption never authorizes work that breaks the code (IRC R105.2). New or moved piping and wiring is a different matter: ordinary repairs never include cutting away a wall or adding, replacing or relocating piping or electric wiring (R105.2.2).
  • Inspection before covering. The rough inspection of plumbing, mechanical, gas and electrical systems is made before covering or concealment, before fixtures or appliances are set, and before the framing inspection. The permit holder or agent tells the building official the work is ready and gives access (R109.1.2, R109.3). Work is not to go past an inspection point without the official's approval, and anything that fails is corrected first (R109.4).
  • Final inspection before occupancy. The model code places it after the permitted work is complete and before occupancy (R109.1.6). In a home you already live in, ask your building department what that means for your job. Where permitted work is done, the model code also calls for smoke alarms, and for carbon monoxide alarms where the home has fuel-fired appliances or an attached garage, placed as in new homes (R314.2.2, R315.2.2 in the 2021 edition).
  • Permits lapse. A model-code permit becomes invalid if work does not start within 180 days of issue, or if 180 days pass between inspections. The official may extend it in writing (R105.5). A schedule with long gaps can run into this, so ask your department how its rule reads.

On health and safety, EPA's lead rule covers paid work that disturbs painted surfaces in homes built before 1978: the firm must be certified and its workers trained in lead-safe practices. EPA says the rule generally does not cover homeowners working on their own home, though it does if you rent out all or part of it. For asbestos, EPA says you cannot tell by looking, recommends considering an inspection by a trained and accredited professional if you plan to remodel, and says sampling is best left to professionals. It also suggests different firms for assessment and for any removal.

Paint, floors and cabinets: why people sequence them differently

There is no code rule for this part, and the sources for this page do not set one. What follows is typical reasoning, and a good contractor may choose differently for your job. What matters is that they have a reason and tell you.

Paint before floors

Typical reason: drips, tape and ladders are hard on a finished floor, so many crews paint walls and ceilings first and lay the floor after. The catch: new floors can scuff fresh paint, so a second touch-up coat often follows. The interior painting page and the paint order calculator cover amounts and coats.

Floors before paint

Typical reason: sanding or finishing a wood floor on site makes dust, and dust settles on wet paint. Some crews finish site-sanded hardwood floors first, protect them, then paint. Which way works depends on the product, so follow the manufacturer's instructions.

Cabinets over the floor or the floor around them

Typical reason for flooring first: one unbroken floor, so a later cabinet change leaves no gap. Typical reason for cabinets first: no cutting the floor around every box. Floor types differ, so see tile floors and vinyl plank and laminate, and use the floor and tile order calculator for quantities.

Custom items set the pace

Typical effect: cabinets and counters made to measure are ordered once the room is ready to measure, so a late item can leave the trades behind it waiting. Ask what is ordered when, and who tells you if a date slips.

Paint and finishes also release gases. EPA says paints, varnishes and wax contain organic solvents, that many such compounds are higher indoors than outdoors, and that you should increase ventilation and follow label precautions while using them. Ask when the rooms you live in get fresh finish.

Who coordinates the trades, and what a change does to the order

Several trades touch the same wall: framer, plumber, electrician, drywall finisher, painter, floor installer. Somebody has to call each of them at the right moment. On many jobs the general contractor does that. On others you are the coordinator, and the plumber's delay is your problem. Ask which it is, and have the contract say so. The bid comparison tool helps line up what each bid does and does not include.

A change late in the order costs more because it undoes finished work. Moving an outlet after the drywall is up means opening the wall. Changes should be written down before work on them starts: see change orders and change orders and payment schedules. Finish items sold as allowances should be chosen early enough to be on site when their step comes up. If you live in the house while this happens, read living through a remodel.

What to ask before you sign, and common mistakes

  1. Can I have the schedule in writing, step by step, with each trade named? This site does not give durations because no source supports a typical number. Your contractor's own schedule should.
  2. Who coordinates the trades, and who do I call if one does not show up?
  3. Who pulls the permit and calls for each inspection, and which inspections does my building department require on this job?
  4. What will you do if an inspection fails, and does the schedule allow for it?
  5. If the house was built before 1978, who holds the lead-safe certification, and what gets tested before demolition?
  6. In which order will paint, floors and cabinets go, and why that order for this job?
  7. Which items are allowances and when must I choose them so they are on site on time?
  8. How is a change after drywall priced, and who signs it?
  • Ordering finishes late, so the crew waits on a part.
  • Closing walls before the rough-in inspection is signed off, which the model code says not to do.
  • Skipping the lead and asbestos question and demolishing first.
  • Paying the last installment before the punch list is done.
  • Treating the order on this page as a promise. Your job's written schedule is the one that counts.

Common questions

Is there one correct order for a remodel?

No. The sequence here is a trade convention. Crews change it for the house, the trades and the materials. The fixed points are the ones set by your building department, such as the permit and the inspections, and by the safety rules for older homes.

When does the inspector come?

The model building code calls for a rough inspection of plumbing, mechanical, gas and electrical work before it is covered, and a final inspection after the permitted work is complete. Your building department says which inspections apply to your job and how to request them.

Do I paint before or after the floors go in?

Both orders are used. A typical reason for painting first is drips on finished floors. A typical reason for floors first is sanding dust on wet paint. Ask your contractor which they plan and why.

How long will each stage take?

Ask for a written schedule. RenovaOak does not give typical durations because we found no source for them, and your house and your trades decide.

Sources

Checked November 20, 2026. Read: the 2021 IRC chapter 1 sections on permits and inspections and chapter 3 sections on alarms (ICC marks the 2021 edition a historical version; the 2024 edition exists, and section numbers can differ), the EPA lead and asbestos pages, and the EPA page on volatile organic compounds. The IRC is a model code, so your state or city decides the edition and changes. Not read: any official source for the usual order of trades, typical durations or curing times, so the sequence here is labeled a trade convention and the reasons for sequencing paint, floors and cabinets are general reasoning. No durations or prices are given on purpose.