Set a remodel budget when no price list exists

Nobody publishes a reliable price for your job, so build the number yourself: scope, written bids, allowances, a line for surprises, and a sheet you keep updating.

By RenovaOak Editorial Team Updated 8 min read

Start with
A written scope
Number comes from
Three written bids
Reserve line
Your own choice
Biggest unknown
What is behind the surface
Illustration: a budget sheet with lines for contract, allowances, permits, temporary living, financing and a reserve, next to a floor plan
A budget is a list of lines. Each line has an owner and a source.

In short

There is no free official price list for interior remodels, and this page does not print one. A budget you can trust starts from a written scope (what is in, what is out), then three written bids on that same scope, compared line by line in the bid comparison tool. Add the lines bids leave out: finish allowances, a reserve for what is behind the walls, permit and inspection fees, temporary living costs and the cost of borrowing. Sort the wish list into must-have, nice-to-have and later, and track every change against the contract.

Scope first: what is in and what is out

A price is an answer to a question, and the question is your scope. Before you ask anyone for a number, write down which rooms, which surfaces and which fixtures the job covers. Then write what it does not cover. "Not included" is where most budget surprises start.

  • In: the rooms, the demolition, the new surfaces, the fixtures and appliances, and who buys each one.
  • Out: things you will do later or yourself, such as painting, trim, or moving furniture and cabinets out of the room.
  • Measured: in square feet of finished floor or wall, by item for fixtures, or as a lump sum for the room. Ask each bidder which unit the number uses. Outside work such as roofing, windows and siding is outside this site's scope.

Give every bidder the same written scope, with the same list of fixtures and finishes. If one bid prices a layout change and another does not, you are comparing two different jobs. The page on what drives remodel prices explains which parts of a scope move the number most, without quoting dollars.

Get three written bids and compare them

With no published price list, your own bids are the only local data that matter. The FTC advises getting multiple written estimates that describe the work, the materials, the completion date and the price. It also says not to pick the lowest bidder automatically, and to ask for an explanation when bids differ by a lot. A large gap often means a different scope or a missing line.

Enter the three bids in the bid comparison tool. It lines them up per square foot and has a contingency field, which you fill with your own number. Then ask each bidder about every line that appears in one bid and not the others. The contractor page covers what to ask a firm before you sign.

The budget sheet, line by line

A budget sheet is a short list with one number per line. Typical lines:

  • Contract price for the written scope, including the allowances inside it.
  • Items you buy yourself and have installed, such as appliances or fixtures outside the contract.
  • Permit and inspection fees. They exist, and they vary by jurisdiction. Your building department can tell you its fee schedule and whether the contractor or you pays them.
  • Temporary living costs: meals while the kitchen is out, a place to bathe, storage, or a short stay elsewhere. Living through a remodel covers the practical side.
  • Cost of borrowing, if you finance. Take the figure from your lender's written terms.
  • Reserve for surprises, covered in the next section. How large it is, is your decision.

Worked example with made-up numbers. The amounts below were chosen to make the sums easy. They say nothing about what any real job costs, and the reserve is a number the reader picked for this example, not a recommendation.

Worked example with made-up numbers: one budget sheet
LineMade-up amountWhere the number comes from
A. Contract price (includes a 2,500 tile allowance)$20,000The accepted written bid
B. Appliances bought outside the contract$3,000Your own list of picks
C. Permit and inspection fees$400Building department fee schedule
D. Temporary living costs$1,200Your own estimate of weeks and meals
E. Cost of borrowing$900Lender's written terms
F. Subtotal (A + B + C + D + E)$25,50020,000 + 3,000 + 400 + 1,200 + 900
G. Reserve for surprises$2,000The reader's own choice, not a recommended amount
H. Budget total (F + G)$27,50025,500 + 2,000

Change the reserve in your own sheet and everything below it changes. Nobody can tell you the right amount for your house, which is why the tool leaves the field to you.

Surprises behind the surface, permits and safety

The reserve line exists because some conditions cannot be priced until the surface comes off. Two common ones have their own pages. Subfloor and moisture checks explains what to look for before new flooring goes down. Lead paint and asbestos in older homes covers houses built before 1978 and older materials.

  • Lead: EPA says anyone paid to disturb painted surfaces in a pre-1978 home must be certified and trained in lead-safe work practices. Ask each bidder whether the price includes lead-safe work.
  • Asbestos: EPA advises considering an inspection by a trained, accredited professional if you plan to remodel, and says not to take samples yourself. If removal is needed, EPA recommends using different firms for the assessment and the removal.
  • Concealed systems: old wiring, pipes or framing are found when walls open. Changes to plumbing, electrical or structure are crew work and should be priced in a written change order.

Permits are a real cost with a real effect on the schedule. Under the model International Residential Code (2021 edition, chapter 1), an owner or agent who alters a building, or installs or replaces electrical, gas, mechanical or plumbing systems, applies to the building official first. The same section exempts "painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work," but ordinary repairs never include cutting into walls or changing piping or wiring. Plumbing, mechanical, gas and electrical rough-in work is inspected before it is covered, so the inspection date sits in your schedule. This is the model code. Your building department decides what applies, what the fees are and whether it grants exceptions. See permits for interior remodels.

Paying for it and what comes back

How you will pay changes the total. CFPB describes a home equity loan as a lump sum borrowed against your equity and a home equity line of credit as a line you draw on repeatedly, usually at an adjustable rate. With an existing mortgage, both are second mortgages paid in addition to the first. CFPB also warns that PACE loans are repaid through property taxes, can raise your tax bill, and are paid ahead of the mortgage if you fall behind. The FTC warns against financing arranged through a contractor without shopping around. Financing a remodel compares the options. Your lender decides what you qualify for.

What returns at sale is a separate question from what the job costs. No remodel is certain to return its cost, and this site does not borrow cost-versus-value tables. Put your own numbers into resale math: your cost, the value you expect it to add, how many years you will stay, and the interest you pay. For the tax side, IRS Publication 523 says the cost of improvements that add to value, prolong useful life or adapt the home to new uses is added to your basis, and it lists kitchen modernization and flooring among examples. It lists painting among repairs that are not added. IRS Topic 701 describes the exclusion of up to $250,000 of gain ($500,000 on a joint return) on a main home, with ownership and use tests. Keep every invoice, and ask a tax professional how this applies to you. More is on resale value and taxes of a remodel.

Sort the wish list and phase the work

When the total is more than you can spend, cut by category, not by squeezing every line. Sort each item into one of three groups before you ask for final bids.

Three groups for the wish list
GroupWhat goes in itTest
Must-haveSafety, water, structure, and the reason you started the projectWould the project fail without it?
Nice-to-haveUpgrades you want if the numbers allowCan it be priced as a separate line?
LaterWork you can do after the main job without redoing itWill it stay accessible when the walls are closed?

Phasing splits one job into two or more. It works when each phase leaves the house safe and usable and the later phase does not require tearing out the first. Anything that hides under a surface, such as wiring, plumbing and blocking for cabinets, usually belongs in the first phase. Cosmetic work can wait. Ask each bidder to price the phases separately, and ask whether a second permit or inspection is needed. Remodel order of work shows the usual sequence. Prices can differ when you come back.

Painting, some trim and some demolition are common homeowner tasks, and your own labor can be a line on the sheet. Electrical, plumbing, structural changes and anything that disturbs lead paint or asbestos should go to qualified professionals. In a pre-1978 home EPA says the lead rule generally does not cover owners working in their own home, but it recommends lead-safe practices and a certified contractor.

Track the budget against the contract

A budget only works if you keep it current. Once you sign, the contract is the first number on the sheet. Every change adds to it, and each one should be a written change order that states the added work, the added cost and any added time, signed before the work starts. The FTC also advises against paying the full amount up front, and says to make the final payment only when the work is done and you are satisfied. Match each payment to finished work, not to a date.

Worked example with made-up numbers: tracking the reserve
EventMade-up amountReserve left
Reserve at the start (the reader's own choice)$2,000$2,000
Tile chosen costs 3,100 against the 2,500 allowance$600$1,400
Rotted subfloor found, approved change order$1,100$300
Contract value now: 20,000 + 600 + 1,100$21,700$300
  1. Record each change order the day you sign it, with its amount and what it replaced.
  2. Subtract it from the reserve, or add it to the sheet if it is outside the reserve.
  3. When the reserve is gone, stop and decide: cut a nice-to-have, move something to a later phase, or find more money. Do it before more work is done.

Common mistakes: comparing bids that have different scopes, accepting an allowance without asking what it covers, leaving permit fees and temporary living costs off the sheet, planning to spend the whole reserve on upgrades, and approving extra work by conversation instead of in writing.

Common questions

How much should I budget for a remodel?

This site does not give a figure, because no free official price list exists and costs vary by house, scope and local labor. Write a scope, get three written bids on it, and compare them in the bid comparison tool. Then add allowances, permit fees, temporary living costs, the cost of borrowing and a reserve you choose.

How big should the contingency line be?

That is your decision, and this page gives no percentage. The more unknowns behind the walls, the more room you may want.

Do permit fees belong in the remodel budget?

Yes. Permit and inspection fees exist and vary by place. Ask your building department for its fee schedule, and ask each bidder in writing whether the price includes the permit.

Should I pay for the remodel with a loan from the contractor?

The FTC advises never agreeing to financing through a contractor without shopping around. Compare it with your own lender's terms and with the options in financing a remodel. Your lender decides what you qualify for.

Sources

Checked November 20, 2026. The IRS Publication 523 and Topic 701 pages, the FTC home improvement page, the EPA lead-safe and asbestos homeowner pages, the two CFPB pages and ICC chapter 1 of the 2021 IRC (marked a historical version by ICC) were read. All dollar amounts in the two examples are made up and are not prices. Not read: any source with remodel costs (none free and official was used), local permit fee schedules, HUD 203(k) and IRS Publication 530, and the federal text of the FTC Cooling-Off Rule. Your building department decides which code edition and fees apply.